Post by TonyV on Dec 1, 2010 11:35:36 GMT -5
Temporary Pre-Build VAT
(Support New Model Pilot Plant for M1 P473 2013 Build)
Department Needs: Trim – 4 Frame –3
Temporary Assignment Period Beginning: January, 2011
Scope of Work:
• Pre-Build VATs from KTP will travel to the New Model Pilot Plant beginning in January, with a tentative schedule to return to KTP by first of March. (Approximately a 6 week program)
• Pre-Build VATs will support the 2013 P473 Super Duty M1 Build at the New Model Pilot Plant.
• Only employees currently within this department are eligible to bid.
• Pre-Build VATs will return to the same team and shift for any return to production at the completion of assignment.
• Note: If at anytime there is inactivity with the M1 P473 Build at the New Model Pilot Plant, the Pre-Build VATs will report back to work on their home team for that temporary period of time.
Personal Commitment:
• Willing to make personal commitment to the process until activities are completed.
• Participate in all phases of product build.
• Be capable of performing all operations in assembly process.
• Participate and assist in problem solving and planning of the assembly process.
• Work overtime as indicated. May include weekends or holidays.
• Be required to adjusted start times of work shift.
• Be available for different shifts if required.
• Ability and willingness to learn and apply basic computer skills.
• Retain current rate of pay.
• Use/wear assigned pager or radio.
Training:
• Be able to talk with operators about their workstation and processes.
• Set up work stations.
• Willing to conduct on the job training and/or assist in classroom training delivery.
• Assist with job training aid, job training sheets (i.e. OIS, JSA)
• Willing to participate in training for self-development if necessary.
• Be willing to work all crews to train employees on each crew as requirements dictate.
Travel:
• Spend extended periods of time away from home in Southeast Michigan as needed.
• Frequent weekends away from home based on need.
• Travel to destinations by means provided.
• Launch management will plan hotel usage.
• Must adhere to Company travel policies.
Note: This bid will not carry over to future pre-builds.
(Support New Model Pilot Plant for M1 P473 2013 Build)
Department Needs: Trim – 4 Frame –3
Temporary Assignment Period Beginning: January, 2011
Scope of Work:
• Pre-Build VATs from KTP will travel to the New Model Pilot Plant beginning in January, with a tentative schedule to return to KTP by first of March. (Approximately a 6 week program)
• Pre-Build VATs will support the 2013 P473 Super Duty M1 Build at the New Model Pilot Plant.
• Only employees currently within this department are eligible to bid.
• Pre-Build VATs will return to the same team and shift for any return to production at the completion of assignment.
• Note: If at anytime there is inactivity with the M1 P473 Build at the New Model Pilot Plant, the Pre-Build VATs will report back to work on their home team for that temporary period of time.
Personal Commitment:
• Willing to make personal commitment to the process until activities are completed.
• Participate in all phases of product build.
• Be capable of performing all operations in assembly process.
• Participate and assist in problem solving and planning of the assembly process.
• Work overtime as indicated. May include weekends or holidays.
• Be required to adjusted start times of work shift.
• Be available for different shifts if required.
• Ability and willingness to learn and apply basic computer skills.
• Retain current rate of pay.
• Use/wear assigned pager or radio.
Training:
• Be able to talk with operators about their workstation and processes.
• Set up work stations.
• Willing to conduct on the job training and/or assist in classroom training delivery.
• Assist with job training aid, job training sheets (i.e. OIS, JSA)
• Willing to participate in training for self-development if necessary.
• Be willing to work all crews to train employees on each crew as requirements dictate.
Travel:
• Spend extended periods of time away from home in Southeast Michigan as needed.
• Frequent weekends away from home based on need.
• Travel to destinations by means provided.
• Launch management will plan hotel usage.
• Must adhere to Company travel policies.
Note: This bid will not carry over to future pre-builds.